The engineers of NIK Ltd prepared the outerwing panel for the installation on Tu-144

2019-07-22 10:52:24

The engineers of NIK Ltd prepared the outerwing panel for the installation on Tu-144

On the 19th of July once again the engineers of NIK Ltd directly participated in preparation of Tu-144 for outerwing panel installation.

The following works have been done:

-They checked the screws of the outerwing panel mooring on working capacity and resource for further use (more than 1000 screws).

-They put up the plane on the tire jacks.

-They did the advance for outerwing panels installation.

Wing butting is planned on the 21th of July from 10 a.m.

 

 

 